06/03/2013:
Order dated March 06, 2013 - Appeal (L) No.50 of 2013 Excellent judgment by Double Bench of Mumbai High Court delivered on 6th March 2013, again Indian Judicial System has come to the rescue of the 45 members of our Society, kudos to Mumbai High Court!!!!
|
 Click to download
|
 |
 |
|
31/01/2013:
Letter issued by Brihan Mumbai Mahanagar Palika to developer and architect based on order given by high court on 29/01/2013.
|
 Click to download
|
 |
 |
|
30/01/2013:
Zenal Construction Pvt Ltd has gone into appeal against the High Court order dated 10th January 2013, which was placed on High Court's double bench board for hearing on 29th January 2013. Dear Members this is the copy of order delivered by Chief Justice Mohit S Shah and Judge Anoop V Mohta. For society members information only.
By Managing Committee.
|
 Click to download
|
 |
 |
|
23/01/2013:
Dear Members,
The developers / builders have not paid the Society's water and Electricity bill hence the said services have been disconnected by the statutory authorities. For information of Motinagar Society Members only.
By Managing Committee.
|
 Click to download
|
 |
 |
|
Court Judgement dated JANUARY 10, 2013.
Dear Members / Visitors, this is the landmark decision from the High Court, Petition (L) No. 1640 of 2012. Judge : R.D. Dhanuka J. ,We all Motinagar Society Members trust the judiciary system, and wish to aggressively perceive the matter until all our legitimate demands per the Agreement for Redevelopment dated 6th April 2008 are complied with.
|
 Click to download |
 |
|
|
|
|